2020 Annual Report
9
Industry Day Kicks off Procurement Process
On August 15, 2019 we hosted an Industry Day for Prospective
Designers and Contractors to initiate the procurement process
for the major elements of the East County AWP Project.
The East County AWP Project consists of three progressive design
build packages. This meeting had
over 100 attendees with interest
in one or more of the packages.
The procurement process
ofcially began in October
2019 and continued into
Fiscal Year 2021.
Critical Service
Agreements Signed
In May 2020, the Joint Powers
Authority Board of Directors
unanimously approved water and
wastewater service agreements,
which are critical to the JPA's
eligibility for key program nancing
opportunities. These agreements
are a prerequisite to obtaining a
credit rating for the JPA, which is
necessary for many nancing
options. They also provide the
necessary nancial commitments
to ensure long-term security of the
JPA's revenues.
million
$528 million
progress!
October 2019 by the U.S.
$342 million in funding
Innovation Act (WIFIA) loans.
Advanced Water Purification Program.
representatives from Padre Dam
City of El Cajon and the
Water District is an
PKG #3
includes retrots
and capacity
expansions of two
lift stations, the
installation of a 3.5
mile
force main,
and residuals
pipeline.
This is an epic day in East
County because water is life and
we are going to provide a new
reliable source of water,
commented Gary Kendrick, JPA Chair
and El Cajon Councilman.
I grew up in Santee and
watched Santee Lakes being
built and lled. We have come a
long way since then and I believe
that our children and our
grandchildren will benet from
important water supply decisions
we are making today.
PKG #2
includes a
10-11 mile long
puried water
pipeline and a
dechlorination
facility.
PKG #1
includes a
16 MGD water
recycling facility,
11.5 MGD advanced
water purication
facility and solids
handling
facility.